Which THREE are formal Scrum ceremonies (events) as defined in the Scrum Guide?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Sprint Planning.

The Scrum Guide defines five formal events: Sprint Planning, Daily Scrum, Sprint Review, Sprint Retrospective, and the Sprint itself. Backlog refinement is not a formal ceremony; it is an ongoing activity. Release planning is not part of Scrum. Therefore, the three correct ceremonies among the options are Sprint Planning (A), Daily Scrum (C), and Sprint Review (D).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Sprint Planning.

    Why this is correct

    Sprint Planning is a Scrum ceremony to plan the work for the sprint.

  • Backlog refinement.

    Why it's wrong here

    Backlog refinement is a practice but not a formal Scrum event.

  • Daily Scrum.

    Why this is correct

    The Daily Scrum is a formal Scrum event because the Scrum Guide mandates it as a 15-minute time-boxed meeting for Developers to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. This satisfies the stem’s constraint requiring only ceremonies explicitly listed in the Guide, distinguishing it from informal stand-ups or ad‑hoc syncs.

  • Sprint Review.

    Why this is correct

    The Sprint Review is held at the end of the sprint to inspect the increment.

  • Release planning.

    Why it's wrong here

    Release planning is not a defined Scrum ceremony.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE are events in the Scrum framework? (Choose three)

easy
  • A.Grooming
  • B.Sprint Retrospective
  • C.Daily Stand-up
  • D.Sprint Planning
  • E.Release Planning

Why B: The correct Scrum events are Sprint Planning, Daily Stand-up (Daily Scrum), and Sprint Retrospective, which correspond to options B, C, and D. Option A (Grooming) is not a Scrum event; backlog refinement is an ongoing activity. Option E (Release Planning) is not part of the Scrum framework; it may be used in other methodologies.