Which THREE are events in the Scrum framework? (Choose three)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Sprint Retrospective
The correct Scrum events are Sprint Planning, Daily Stand-up (Daily Scrum), and Sprint Retrospective, which correspond to options B, C, and D. Option A (Grooming) is not a Scrum event; backlog refinement is an ongoing activity. Option E (Release Planning) is not part of the Scrum framework; it may be used in other methodologies.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Grooming
Why it's wrong here
Grooming (backlog refinement) is not an official Scrum event.
- ✓
Sprint Retrospective
Why this is correct
Sprint Retrospective is a Scrum event.
- ✓
Daily Stand-up
Why this is correct
The Daily Stand-up (Daily Scrum) is a Scrum event.
- ✓
Sprint Planning
Why this is correct
Sprint Planning is a Scrum event.
- ✗
Release Planning
Why it's wrong here
Release Planning is not a Scrum event.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →