In a predictive project, the project manager must formally accept the project's deliverables. Which process group does this activity belong to?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Closing

Formal acceptance of deliverables occurs during the Closing process group, specifically in the Validate Scope and Close Project processes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executing

    Why it's wrong here

    Executing produces deliverables, but formal acceptance is later.

  • Closing

    Why this is correct

    Correct: Deliverables are formally accepted during project or phase closing.

  • Planning

    Why it's wrong here

    Planning defines how acceptance will be performed, but not the actual acceptance.

  • Initiating

    Why it's wrong here

    Initiating authorizes the project, not acceptance.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.