In a predictive project, the project manager must formally accept the project's deliverables. Which process group does this activity belong to?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Closing
Formal acceptance of deliverables occurs during the Closing process group, specifically in the Validate Scope and Close Project processes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Executing
Why it's wrong here
Executing produces deliverables, but formal acceptance is later.
- ✓
Closing
Why this is correct
Correct: Deliverables are formally accepted during project or phase closing.
- ✗
Planning
Why it's wrong here
Planning defines how acceptance will be performed, but not the actual acceptance.
- ✗
Initiating
Why it's wrong here
Initiating authorizes the project, not acceptance.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.