CAPM Predictive Plan-Based Methodologies Practice Question

In a predictive project, the project manager must formally accept the project's deliverables. Which process group does this activity belong to?

⚠ Common exam trap

CAPM often tests the confusion between Executing and Closing, where candidates mistakenly associate deliverable acceptance with the Executing process group because that is where the work is performed, rather than with the formal acceptance that occurs in Closing.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Closing

Formal acceptance of project deliverables is a key activity within the Closing process group. In predictive projects, the Closing process group includes the process 'Close Project or Phase,' where the project manager obtains final acceptance of the product, service, or result from the customer or sponsor. This ensures that all requirements are met and the project can be formally closed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executing

    Why it's wrong here

    Deliverable acceptance belongs to Closing, where the Verify Scope and Close Project processes run. Executing is tempting because that is where the work producing deliverables happens, yet acceptance is a distinct authorisation step performed after completion.

  • ✓

    Closing

    Why this is correct

    Formal acceptance of deliverables occurs in the Closing process group, where the project manager obtains sign-off and verifies that completed products meet requirements before administrative closure. This satisfies the stem's predictive lifecycle constraint, since acceptance is a defined Closing activity rather than Monitoring and Controlling work.

  • ✗

    Planning

    Why it's wrong here

    Formal deliverable acceptance and sign-off occur in the Monitoring and Controlling process group, where scope verification is performed. Planning produces the scope baseline and acceptance criteria but does not accept completed deliverables. Planning would be correct if the question asked where acceptance criteria are defined.

  • ✗

    Initiating

    Why it's wrong here

    Formal acceptance of deliverables occurs in Closing, not Initiating, which authorises the project and defines its charter. Initiating is tempting because it also involves formal approval, but of the project itself rather than its outputs.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint