CAPM Business Analysis Frameworks Practice Question
Which THREE items are typically included in a business analysis plan? (Choose three.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Deliverables and artifacts
Options A, B, and C are correct because a business analysis plan typically includes deliverables and artifacts, stakeholder list and roles, and requirements prioritization criteria. Option D (Budget estimates) is part of the project budget, not the business analysis plan. Option E (Detailed project schedule) is part of the project management plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Deliverables and artifacts
Why this is correct
The plan lists what the business analysis will produce.
- ✓
Stakeholder list and roles
Why this is correct
Stakeholder identification and roles are essential for analysis activities.
- ✓
Requirements prioritization criteria
Why this is correct
Prioritization criteria guide decision-making.
- ✗
Budget estimates
Why it's wrong here
Budget is part of the project financial plan.
- ✗
Detailed project schedule
Why it's wrong here
Detailed schedule is developed by the project manager.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.