Courseiva
Predictive Plan-Based MethodologieshardMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

During the planning phase of a predictive project, the project manager wants to define the project scope more precisely. Which process should be used to develop a detailed description of the project and product?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Define Scope

Define Scope is the process of developing a detailed project scope statement that describes the project and product boundaries.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Define Scope

    Why this is correct

    Correct: This process produces the project scope statement.

  • Collect Requirements

    Why it's wrong here

    Collect Requirements gathers stakeholder needs but does not define scope.

  • Create WBS

    Why it's wrong here

    Create WBS decomposes scope into work packages, but the scope is already defined.

  • Validate Scope

    Why it's wrong here

    Validate Scope is about formal acceptance, not initial definition.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.