Question 50 of 503

Quick Answer

The answer is 6.67 days. This result comes from the PERT three-point estimate calculation, which uses a weighted average formula: (Optimistic + 4×Most Likely + Pessimistic) / 6. By plugging in the values—4 days optimistic, 6 days most likely, and 12 days pessimistic—you get (4 + 24 + 12) / 6 = 40 / 6, which equals 6.67 days. On the Certified Associate in Project Management CAPM exam, this question tests your ability to apply the PERT technique for activity duration estimation, a key concept in the Schedule Management knowledge area. A common trap is confusing the PERT formula with a simple average; remember that the most likely estimate is weighted four times heavier to reflect realistic uncertainty. For a quick memory tip, think of the mnemonic “O + 4M + P over 6” to keep the order and weighting straight.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is estimating the duration of an activity. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the PERT three-point estimate, what is the expected duration?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

6.67 days

The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (4 + 4×6 + 12) / 6 = (4 + 24 + 12) / 6 = 40 / 6 = 6.67 days. This weighted average gives more influence to the most likely estimate, providing a realistic expected duration.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 6.67 days

    Why this is correct

    Correct PERT calculation: (4 + 4*6 + 12)/6 = 6.67.

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 12 days

    Why it's wrong here

    This is the pessimistic estimate.

  • 7.33 days

    Why it's wrong here

    This would be the simple average.

  • 6 days

    Why it's wrong here

    This is the most likely estimate.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly use a simple average (add all three and divide by 3) instead of the weighted PERT formula, leading them to choose 7.33 days.

Detailed technical explanation

How to think about this question

The PERT (Program Evaluation and Review Technique) formula assumes a beta distribution, which is more realistic for project tasks than a normal distribution because it can be skewed. The weights (1,4,1) reflect that the most likely estimate is four times as probable as the extremes, and dividing by 6 normalizes the sum. In real-world scenarios, this method helps project managers account for uncertainty in tasks like software development or construction, where optimistic and pessimistic outcomes are possible.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 6.67 days — The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (4 + 4×6 + 12) / 6 = (4 + 24 + 12) / 6 = 40 / 6 = 6.67 days. This weighted average gives more influence to the most likely estimate, providing a realistic expected duration.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project manager is estimating activity durations. The team provides three estimates: optimistic 10 days, pessimistic 20 days, most likely 14 days. Using the PERT beta distribution, what is the expected duration?

medium
  • A.14 days
  • B.14.67 days
  • C.15 days
  • D.14.33 days

Why D: Option D is correct. PERT expected = (O + 4M + P)/6 = (10 + 4*14 + 20)/6 = (10 + 56 + 20)/6 = 86/6 = 14.33 days.

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.