Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project team is conducting cost estimation for a project that uses a predictive lifecycle. They have historical data from similar projects. Which estimation technique is MOST appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analogous estimating

Analogous estimating uses historical data from similar projects, making it the most appropriate technique for this scenario. Option B is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Three-point estimating

    Why it's wrong here

    Three-point uses optimistic, pessimistic, and most likely, not historical data.

  • Analogous estimating

    Why this is correct

    Analogous uses historical data from similar projects.

  • Parametric estimating

    Why it's wrong here

    Parametric uses statistical relationships, not directly from similar projects.

  • Bottom-up estimating

    Why it's wrong here

    Bottom-up is detailed and requires decomposition.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.