A project manager is reviewing the project schedule and notices that a task has a lead time of 2 days. What does this indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The task can start 2 days before its predecessor finishes
Lead time allows a successor activity to start before its predecessor finishes. A lead of 2 days means the successor can start 2 days before the predecessor finishes. Lag is the opposite (wait time). Float is not directly related.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The task has 2 days of float
Why it's wrong here
Float is schedule slack, expressed as total or free float, and is unrelated to lead time. The term tempts anyone conflating timing adjustments with buffer, but lead time specifically advances a successor's start relative to its predecessor.
- ✗
The task duration is 2 days
Why it's wrong here
Duration is the elapsed working time a task takes to complete, whereas lead time is a scheduling dependency offset. The confusion arises because both are expressed in days, but a two-day lead does not set the task's own duration.
- ✗
The task cannot start until 2 days after its predecessor finishes
Why it's wrong here
A lead time of 2 days means the successor can begin 2 days before its predecessor finishes — an overlap, not a delay. This option describes lag, which inserts waiting time between activities. Lag would be correct if the schedule required a mandatory pause, such as curing concrete before inspection.
- ✓
The task can start 2 days before its predecessor finishes
Why this is correct
Lead time allows a successor task to begin before its predecessor completes, overlapping the two by two days. This satisfies the schedule constraint described in the stem, where the task starts early rather than waiting. It contrasts with lag, which imposes a delay between activities.
Go deeper
Related to this question
About these practice questions
One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.