CAPM Predictive Plan-Based Methodologies Practice Question

During project execution, a stakeholder requests a new feature that was not in the original scope. The project manager determines that the feature can be accommodated without affecting the critical path, but will increase costs. According to the predictive plan-based methodology, what should the project manager do NEXT?

⚠ Common exam trap

CAPM often tests the misconception that a project manager can approve changes that do not affect the critical path or that stakeholder satisfaction justifies bypassing formal change control; the trap is forgetting that any change affecting baselines requires CCB approval.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Submit the change request to the change control board

In a predictive (plan-based) methodology, any change to the project scope, schedule, or cost must go through the formal Integrated Change Control process. Since the requested feature was not in the original scope and will increase costs, it constitutes a change request. The project manager's next step is to submit this change request to the Change Control Board (CCB), which is the designated body responsible for reviewing, approving, or rejecting changes that impact project baselines. The project manager does not have the authority to unilaterally approve changes that affect cost baselines, even if the critical path is unaffected.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Approve the change to improve stakeholder satisfaction

    Why it's wrong here

    Approving the change bypasses the integrated change control process, which requires a formal change request, impact analysis and approval by the change control board before any scope or cost baseline is modified. It is tempting because stakeholder satisfaction matters, but unilateral approval would be correct only if the project manager held delegated authority to accept scope changes.

  • ✗

    Inform the stakeholder that the change cannot be accepted

    Why it's wrong here

    Rejecting the change outright ignores the integrated change control process, which requires the request to be documented, assessed and decided by the change control board rather than dismissed by the project manager. It is tempting because the feature is out of scope, but refusal would be correct only if the request had already been evaluated and formally declined.

  • ✓

    Submit the change request to the change control board

    Why this is correct

    Any scope addition altering cost must pass through integrated change control before work begins. The change control board evaluates, approves or rejects the request and authorises corresponding baseline updates. Proceeding without approval bypasses governance, regardless of critical path impact.

  • ✗

    Update the project management plan to include the feature

    Why it's wrong here

    Updating the project management plan directly skips the perform integrated change control process, where the change request must first be reviewed and approved before baselines are modified. It is tempting because the feature fits without affecting the critical path, but direct updating would be correct only after the change control board has authorised the change.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.