Which THREE of the following are processes that belong to the Planning process group?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Sequence Activities

Options B, C, and E are correct. Create WBS, Sequence Activities, and Estimate Activity Resources are all Planning processes. Develop Project Charter is Initiating, and Control Quality is Monitoring and Controlling.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Control Quality

    Why it's wrong here

    Control Quality is part of Monitoring and Controlling.

  • Sequence Activities

    Why this is correct

    Sequence Activities is a Planning process under Schedule Management.

  • Estimate Activity Resources

    Why this is correct

    Estimate Activity Resources is a Planning process under Resource Management.

  • Develop Project Charter

    Why it's wrong here

    Develop Project Charter is part of the Initiating process group.

  • Create WBS

    Why this is correct

    Create WBS is a Planning process under Scope Management.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.