CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which THREE of the following are processes that belong to the Planning process group?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Sequence Activities
Options B, C, and E are correct. Create WBS, Sequence Activities, and Estimate Activity Resources are all Planning processes. Develop Project Charter is Initiating, and Control Quality is Monitoring and Controlling.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Control Quality
Why it's wrong here
Control Quality is part of Monitoring and Controlling.
- ✓
Sequence Activities
Why this is correct
Sequence Activities is a Planning process under Schedule Management.
- ✓
Estimate Activity Resources
Why this is correct
Estimate Activity Resources is a Planning process under Resource Management.
- ✗
Develop Project Charter
Why it's wrong here
Develop Project Charter is part of the Initiating process group.
- ✓
Create WBS
Why this is correct
Create WBS is a Planning process under Scope Management.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.