A project is in the execution phase. The earned value analysis shows a Cost Performance Index (CPI) of 0.8 and a Schedule Performance Index (SPI) of 0.9. What is the best interpretation of these metrics?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and behind schedule.

A CPI of 0.8 (less than 1) indicates the project is over budget (cost overrun), and an SPI of 0.9 (less than 1) indicates the project is behind schedule. Option B is wrong because it claims the project is under budget, but CPI < 1 means over budget. Option C is wrong because it claims ahead of schedule, but SPI < 1 means behind schedule. Option D is wrong because it claims both under budget and ahead of schedule, which is the opposite of the metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget and behind schedule.

    Why this is correct

    CPI = 0.8 means the project is over budget (cost overrun), SPI = 0.9 means behind schedule.

  • The project is under budget but behind schedule.

    Why it's wrong here

    CPI < 1 indicates over budget, not under budget.

  • The project is over budget but ahead of schedule.

    Why it's wrong here

    SPI < 1 indicates behind schedule, not ahead.

  • The project is under budget and ahead of schedule.

    Why it's wrong here

    CPI < 1 indicates over budget, not under budget; SPI < 1 indicates behind schedule.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.