Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A software development project is facing high uncertainty in requirements. The team is experienced and prefers frequent feedback. Which project life cycle approach is most appropriate?

⚠ Common exam trap

CAPM often tests the distinction between iterative (refining the same solution) and adaptive (embracing change and frequent feedback), so candidates who see 'frequent feedback' and pick iterative miss the uncertainty dimension that points to adaptive.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Adaptive (agile) life cycle

An adaptive (agile) life cycle is designed for environments with high uncertainty and evolving requirements, delivering value through short iterations with frequent stakeholder feedback. Because the team is experienced and prefers frequent feedback, agile approaches like Scrum or Kanban fit best — requirements are refined continuously rather than baselined upfront. This aligns with PMBOK's guidance that adaptive life cycles are chosen when change is expected and rapid delivery of value is prioritized.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Incremental life cycle

    Why it's wrong here

    Incremental life cycles deliver functionality in successive slices, but each slice is planned against a known overall scope, so requirements are largely defined upfront. With high uncertainty and a preference for frequent feedback, the team needs scope re-planned each cycle, which incremental delivery does not provide.

  • ✓

    Adaptive (agile) life cycle

    Why this is correct

    An adaptive life cycle delivers work in short iterations with continuous stakeholder feedback, letting requirements emerge as understanding grows. This suits high uncertainty combined with an experienced team that prefers frequent feedback, unlike predictive or hybrid approaches.

  • ✗

    Iterative life cycle

    Why it's wrong here

    Iterative life cycles deliver a working increment each iteration but re-plan scope progressively rather than freezing it, so they handle uncertain requirements well. The stem's high uncertainty and appetite for frequent feedback point to an adaptive approach; iterative is adaptive, so this is not the failing option here.

  • ✗

    Predictive life cycle

    Why it's wrong here

    Predictive life cycles fix scope, schedule and cost early, then execute against that baseline, so late requirement changes trigger costly change control. It suits stable, well-understood work with low uncertainty. Here requirements are highly uncertain and the team wants frequent feedback, which predictive delivery cannot accommodate.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.