Courseiva
Business Analysis FrameworkshardMultiple ChoiceObjective-mapped

CAPM Requirements Traceability Matrix Practice Question

Exhibit

R1# show ip ospf neighbor
Neighbor ID     Pri   State       Dead Time   Address         Interface
10.1.1.2         1   FULL/DR     00:00:36    192.168.1.2     GigabitEthernet0/0
10.1.1.3         1   2WAY/DROTHER 00:00:39   192.168.1.3     GigabitEthernet0/0
10.1.1.4         1   FULL/BDR    00:00:34    192.168.1.4     GigabitEthernet0/0
10.1.1.5         1   DOWN        -           192.168.1.5     GigabitEthernet0/0

A business analyst is reviewing the output of a requirements validation session. The following issues were identified: 'Requirement REQ-001 has no associated business objective', 'Requirement REQ-002 has a conflicting priority with REQ-003'. What is the most likely cause of these issues?

⚠ Common exam trap

Candidates might assume that missing business objectives indicate a scope problem, but the RTM is the specific tool that captures these links.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The requirements traceability matrix was not properly maintained.

The requirements traceability matrix (RTM) is a tool used to ensure that each requirement is linked to a business objective and that dependencies and conflicts are identified. The issues described—missing links and conflicting priorities—are typical signs of a poorly maintained RTM. Option D correctly identifies this cause. Option A is incorrect because scope statement incompleteness might cause missing requirements, but not specifically the linkage issues. Option B is incorrect because the requirements management plan dictates processes, but the specific tool (RTM) is the issue. Option C is incorrect because templates provide structure, but not maintenance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project scope statement is incomplete.

    Why it's wrong here

    The project scope statement defines the boundaries of the project, but the specific issue of missing links to business objectives is better addressed by the RTM.

  • The requirements management plan was not followed.

    Why it's wrong here

    While the requirements management plan outlines the approach, the symptoms point to a specific artifact (RTM) not being maintained.

  • The business analyst did not use a standard template.

    Why it's wrong here

    Using a standard template can help, but the problem is about the content and updates of the RTM, not the template itself.

  • The requirements traceability matrix was not properly maintained.

    Why this is correct

    Correct. The RTM is designed to track relationships between requirements and business objectives, and conflicts in priorities are also managed in the RTM.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.