Which TWO of the following are outputs of the 'Define Activities' process in predictive project management?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Activity attributes

Options B and D are correct. The Define Activities process in predictive project management outputs the activity list and activity attributes. Option A (project schedule) is an output of the Develop Schedule process. Option C (work breakdown structure) is an input to Define Activities. Option E (resource breakdown structure) is an output of the Estimate Activity Resources process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project schedule

    Why it's wrong here

    The project schedule is an output of Develop Schedule, not Define Activities.

  • Activity attributes

    Why this is correct

    Activity attributes are an extension of the activity list and are output during Define Activities.

  • Work breakdown structure

    Why it's wrong here

    The WBS is an input to Define Activities, not an output.

  • Activity list

    Why this is correct

    The 'Define Activities' process in predictive project management decomposes work packages from the Work Breakdown Structure (WBS) into individual schedule activities. The activity list is a direct output because it documents every activity required to produce the project deliverables, satisfying the constraint that the process must produce a comprehensive, itemised inventory of work for subsequent sequencing and estimation.

  • Resource breakdown structure

    Why it's wrong here

    The Resource Breakdown Structure (RBS) is not an output of 'Define Activities' because that process produces the activity list, activity attributes, and the milestone list; the RBS is instead created during 'Estimate Costs' to hierarchically categorise resources by type. It tempts because it is a structured decomposition document, similar in format to the Work Breakdown Structure (WBS) used in scope definition, but its purpose is cost estimation, not activity identification.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.