A project manager is leading a construction project to build a new bridge. The project sponsor asks the project manager to create a document that formally authorizes the project and gives the project manager the authority to apply organizational resources to project activities. Which document should the project manager produce?

⚠ Common exam trap

Watch out — candidates often confuse the project charter with the project management plan, as both are key documents but only the charter provides formal authorization and authority.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is the formal document that authorizes the project and gives the project manager the authority to apply organizational resources to project activities. It is typically issued by the sponsor or initiator and is essential for the project manager to proceed. The business case and benefits management plan are inputs to developing the charter, while the project management plan is created later to guide execution and control.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Business case

    Why it's wrong here

    The business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition. It is often a predecessor to the project charter and helps justify the project, but it does not formally authorize the project or give the project manager authority over resources. The sponsor's request is for authorization, which the business case does not provide.

  • ✓

    Project charter

    Why this is correct

    The project charter is the document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It is typically issued by the project sponsor or initiator and is a key input to the Develop Project Charter process. In this scenario, the sponsor specifically requests a document to authorize the project and grant authority, which is exactly the purpose of the project charter.

  • ✗

    Benefits management plan

    Why it's wrong here

    The benefits management plan describes how and when the benefits of the project will be delivered and how they will be measured. It is a strategic document that may inform the project charter, but it does not authorize the project or grant the project manager authority to apply resources. The scenario requires a formal authorization document, which is not the benefits management plan.

  • ✗

    Project management plan

    Why it's wrong here

    The project management plan describes how the project will be executed, monitored, controlled, and closed. It is not the document that formally authorizes the project or grants the project manager authority. The project management plan is created after the project charter and integrates all subsidiary plans. While important, it does not serve the authorization purpose described in the scenario.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint