Courseiva
Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

In a predictive project, the project manager needs to estimate the cost of each work package with a high level of accuracy. Which technique is most appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Bottom-up estimating

Bottom-up estimating provides the highest accuracy by estimating costs at the work package level and summing them.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Bottom-up estimating

    Why this is correct

    Correct: Estimates each work package individually for high accuracy.

  • Parametric estimating

    Why it's wrong here

    Parametric uses statistical models; less accurate than bottom-up for detailed estimates.

  • Expert judgment

    Why it's wrong here

    Expert judgment is subjective and not a standalone detailed estimating technique.

  • Three-point estimating

    Why it's wrong here

    Three-point estimating provides a range, not single-point accuracy.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.