During the planning phase of a predictive project, the project manager notices that the project schedule does not include all required deliverables. What is the most appropriate action to address this gap?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the work breakdown structure (WBS) to ensure all deliverables are represented.

The work breakdown structure (WBS) is the foundation for identifying all deliverables and work packages. The schedule is built from the WBS, so if deliverables are missing, the WBS should be reviewed first. Option A is incorrect because directly updating the schedule without proper decomposition can lead to an incomplete baseline. Option B is incorrect because the project charter is a high-level authorization document and does not detail deliverables; changes to deliverables should be managed through change control after the WBS is reviewed. Option C is incorrect because adding resources does not address the root cause of missing deliverables; the WBS needs to be accurate first.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the schedule to include the missing deliverables directly.

    Why it's wrong here

    Updating the schedule without first verifying the WBS could lead to scope creep.

  • Request a change to the project charter to accommodate the missing deliverables.

    Why it's wrong here

    The project charter is a high-level document; changing it is not the immediate step for missing deliverables.

  • Review the scope statement and add more resources to the project.

    Why it's wrong here

    Adding resources does not identify missing deliverables; the scope statement is already approved.

  • Review the work breakdown structure (WBS) to ensure all deliverables are represented.

    Why this is correct

    The WBS captures all deliverables; if it is incomplete, the schedule will be incomplete.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.