Courseiva
Business Analysis FrameworksmediumMultiple ChoiceObjective-mapped

CAPM Business Analysis Frameworks Practice Question

Which tool is used to visually represent the relationships between requirements and other project artifacts?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

RTM

The Requirements Traceability Matrix (RTM) is a grid that links requirements to their origin, design, development, and testing artifacts.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • WBS

    Why it's wrong here

    WBS decomposes project work, not requirements relationships.

  • RTM

    Why this is correct

    RTM provides a structured view of relationships between requirements and other work products.

  • Network diagram

    Why it's wrong here

    Network diagram shows task dependencies, not requirements.

  • Gantt chart

    Why it's wrong here

    Gantt chart shows schedule, not traceability.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.