Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which THREE are common project constraints that must be balanced?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Time

The three common project constraints are time (option C), cost (option D), and scope (option E), collectively known as the triple constraint. Risk (option A) is an uncertainty factor, not a constraint, and quality (option B) is often considered an outcome or a constraint that is balanced within the triple constraint, but it is not one of the three primary constraints.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk

    Why it's wrong here

    Risk is a factor, not a constraint.

  • Quality

    Why it's wrong here

    Quality is often considered a constraint but not part of the classic triple.

  • Time

    Why this is correct

    Schedule duration.

  • Cost

    Why this is correct

    Budget allocated.

  • Scope

    Why this is correct

    Defines what must be delivered.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.