A project manager is determining the sequence of activities for a construction project. Which tool is best suited for this purpose?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Network diagram

A network diagram shows the logical relationships and sequence of activities, making it ideal for sequencing.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Resource breakdown structure

    Why it's wrong here

    RBS categorizes resources, not activity sequencing.

  • Work breakdown structure

    Why it's wrong here

    WBS is a deliverable-oriented decomposition, not a sequence of activities.

  • Gantt chart

    Why it's wrong here

    Gantt charts show schedule over time but not dependencies as clearly as network diagrams.

  • Network diagram

    Why this is correct

    Correct: Network diagrams depict activity dependencies and the critical path.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.