CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which of the following is a characteristic of the project life cycle?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Projects are temporary and unique
Projects are defined as temporary endeavors with a unique product, service, or result. Option A is incorrect because project phases can overlap in iterative or adaptive life cycles. Option C is incorrect because projects are unique and not repetitive; operations produce the same product repeatedly. Option D is incorrect because while projects have a defined end, the exact end date may be adjusted, but the key characteristic is temporary, not a fixed date.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project phases are always sequential
Why it's wrong here
Phases can overlap or run iteratively, as in agile or rolling-wave approaches, so strict sequencing is not a defining characteristic. Sequential progression applies to a predictive waterfall life cycle only; the general characteristic is that phases vary by project and may be concurrent.
- ✓
Projects are temporary and unique
Why this is correct
The project life cycle spans initiation to closure, and its defining characteristics derive from projects being temporary, with definite start and end, and unique, producing a distinct deliverable. This constraint distinguishes project work from ongoing operational activities that repeat indefinitely.
- ✗
Projects produce the same product repeatedly
Why it's wrong here
Projects are undertaken to create a unique product, service or result, so repeated identical output describes operations or manufacturing, not a project life cycle. Repetition belongs to ongoing operational work, whereas the life cycle spans initiating, planning, executing, monitoring and closing for one unique deliverable.
- ✗
Projects have a fixed end date
Why it's wrong here
A fixed end date describes the project itself, not the life cycle, which is defined by the sequence of phases (initiation, planning, execution, closure) and varying cost/resource levels. It is tempting because projects are temporary endeavours, so a defined endpoint is a genuine project attribute — but that is a project characteristic, not a life-cycle characteristic.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.