CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project manager is leading a project to develop a new mobile application. The project sponsor asks for a document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. Which document should the project manager provide?

⚠ Common exam trap

A common mix-up: candidates confuse the project charter with the project management plan, which are distinct documents with different purposes and timing.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is the formal document that authorizes the project and assigns the project manager the authority to use organizational resources. It is created during the Initiating process group and is essential for legitimizing the project. The other documents, while important, serve different purposes and do not provide the formal authorization required.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project management plan

    Why it's wrong here

    The project management plan is a comprehensive document that describes how the project will be executed, monitored, and controlled. It integrates all subsidiary plans and baselines. However, it does not formally authorize the project or grant the project manager authority. That authorization comes from the project charter, which is typically created before the project management plan is developed.

  • ✓

    Project charter

    Why this is correct

    The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It is a key input to developing the project management plan and serves as the foundation for the project.

  • ✗

    Business case

    Why it's wrong here

    The business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities. It justifies the project but does not formally authorize it or grant authority to the project manager.

  • ✗

    Benefits management plan

    Why it's wrong here

    The benefits management plan describes how and when the benefits of the project will be delivered and how they will be measured. It is a component of the project business documents and helps ensure the project delivers the intended value. It does not authorize the project or give the project manager authority over resources.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.