Courseiva
Agile Frameworks and MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Agile Frameworks and Methodologies Practice Question

An agile team is using a burndown chart for the first time. After six days of a two-week sprint, the burndown chart shows that the remaining work has increased compared to the previous day. The team is confused. They had completed several tasks, but new tasks were added to the sprint backlog after the sprint started. The product owner says the additions were urgent and necessary. The development team is frustrated because they feel the sprint goal is at risk. The Scrum Master must address this situation. What should the Scrum Master do?

⚠ Common exam trap

Many exam-takers assume the sprint backlog is completely frozen once the sprint starts, but Scrum allows changes as long as the team and product owner agree and the sprint goal remains viable.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Ask the product owner and team to renegotiate the sprint scope, either removing some planned work or deferring the new work to the next sprint

The Scrum Master should facilitate a negotiation between the product owner and the development team to re-evaluate the sprint backlog. In Scrum, the sprint backlog can be clarified or renegotiated with the product owner, but the sprint goal must remain achievable. By asking the team and product owner to either remove planned work or defer the new tasks, the Scrum Master protects the sprint goal and maintains team focus, which is the core responsibility of the Scrum Master in an agile framework.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the team to ignore the burndown chart and focus on delivering the original sprint goal

    Why it's wrong here

    Ignoring the chart hides the problem; the team should address the scope change openly.

  • Explain to the product owner that the sprint backlog is frozen once the sprint starts and cannot be changed

    Why it's wrong here

    While scope should be stable, the product owner can negotiate changes if the team agrees and removes equivalent work; absolute freezing is not Scrum.

  • Ask the product owner and team to renegotiate the sprint scope, either removing some planned work or deferring the new work to the next sprint

    Why this is correct

    Scrum allows the product owner to change the sprint backlog only if the team agrees and adjusts scope accordingly.

  • Manually adjust the burndown chart to show the completed tasks and hide the additional work

    Why it's wrong here

    This is dishonest and undermines transparency, a core agile value.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.