A project manager is closing a phase in a predictive life cycle. Which document should be updated to record lessons learned for future phases?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Lessons learned register

Lessons learned are captured in the lessons learned register throughout the project and used to improve future performance.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why it's wrong here

    The project charter authorizes the project and is not updated with lessons learned.

  • Lessons learned register

    Why this is correct

    Correct: The lessons learned register is the repository for such information.

  • Risk register

    Why it's wrong here

    The risk register tracks individual risks, not general lessons.

  • Issue log

    Why it's wrong here

    The issue log documents issues, not lessons learned.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.