Courseiva
Predictive Plan-Based MethodologieshardMultiple SelectObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

Which THREE of the following are key components of a project management plan for a predictive project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule baseline

The project management plan includes subsidiary management plans (e.g., scope, schedule, cost, quality, etc.) and baselines (scope, schedule, cost). The risk register is a project document, not part of the plan. The cost performance index is a performance measure, not a plan component.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule baseline

    Why this is correct

    The schedule baseline is a component of the project management plan.

  • Quality management plan

    Why this is correct

    The quality management plan is a subsidiary plan within the project management plan.

  • Cost performance index

    Why it's wrong here

    CPI is an earned value metric, not a component of the plan.

  • Risk register

    Why it's wrong here

    The risk register is a project document, not part of the project management plan.

  • Scope management plan

    Why this is correct

    The scope management plan is a subsidiary plan within the project management plan.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are components of the project management plan?

medium
  • A.Schedule baseline
  • B.Quality metrics
  • C.Risk register
  • D.Cost baseline
  • E.Scope baseline

Why A: Options A, D, and E are correct. The project management plan includes baselines (scope, schedule, cost) as core components. Quality metrics (B) are part of the quality management plan, which is a subsidiary plan, but not a standalone component of the PM plan. The risk register (C) is a project document, not a component of the project management plan.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.