The correct answer is that the Sprint Backlog includes tasks decomposed from user stories, and it is owned by the Development Team. These two statements are true because the Sprint Backlog is a detailed plan created during Sprint Planning, where the team breaks down selected Product Backlog items into smaller, actionable tasks. On the CAPM exam, this question tests your understanding of Scrum artifacts and accountabilities, often appearing as a trap where candidates mistakenly think the Product Owner owns the Sprint Backlog or that it cannot be changed mid-Sprint. In reality, the Development Team owns and can modify the Sprint Backlog as needed to meet the Sprint Goal, and it is more than just a subset of the Product Backlog—it includes the delivery plan. A helpful memory tip: remember that the Sprint Backlog is the team’s “living to-do list” that they own and update, not a static document locked by the Product Owner.

CAPM Agile Frameworks and Methodologies Practice Question

This CAPM practice question tests your understanding of agile frameworks and methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO statements about the Sprint Backlog are true? (Select TWO)

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

It is created during Sprint Planning.

Options B and D are correct. The Sprint Backlog is created during Sprint Planning and includes decomposed tasks. Option A is false because the Development Team owns the Sprint Backlog. Option C is false because the team can modify it during the Sprint. Option E is false because the Sprint Backlog includes not only selected Product Backlog items but also the plan for delivering them, so it is more than a subset.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • It is a subset of the Product Backlog.

    Why it's wrong here

    The Sprint Backlog includes the selected items and the plan; it is not simply a subset because it contains additional task details.

  • It is created during Sprint Planning.

    Why this is correct

    During Sprint Planning, the team selects items and creates a plan, which becomes the Sprint Backlog.

    Related concept

    Read the scenario before looking for a memorised answer.

  • It includes tasks decomposed from user stories.

    Why this is correct

    The Sprint Backlog often contains tasks that break down the selected Product Backlog items into work units.

    Related concept

    Read the scenario before looking for a memorised answer.

  • It is owned by the Product Owner.

    Why it's wrong here

    The Sprint Backlog is owned by the Development Team; the Product Owner owns the Product Backlog.

  • It cannot be changed during the Sprint.

    Why it's wrong here

    The Development Team can update the Sprint Backlog throughout the Sprint as they learn more.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Agile Frameworks and Methodologies — This question tests Agile Frameworks and Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: It is created during Sprint Planning. — Options B and D are correct. The Sprint Backlog is created during Sprint Planning and includes decomposed tasks. Option A is false because the Development Team owns the Sprint Backlog. Option C is false because the team can modify it during the Sprint. Option E is false because the Sprint Backlog includes not only selected Product Backlog items but also the plan for delivering them, so it is more than a subset.

What should I do if I get this CAPM question wrong?

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.