Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

The sponsor is concerned about the accuracy of cost estimates prepared using analogous estimating. Which estimating technique should the project manager recommend to improve accuracy?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Bottom-up estimating

Bottom-up estimating involves detailed analysis of each work package, providing the highest accuracy. This technique improves upon analogous estimating by using detailed estimates from lower-level components.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reserve analysis

    Why it's wrong here

    Reserve analysis adds contingency, but does not improve the base estimate accuracy.

  • Bottom-up estimating

    Why this is correct

    Bottom-up estimating uses detailed cost data from individual work packages, offering the highest accuracy.

  • Parametric estimating

    Why it's wrong here

    Parametric is a statistical method but may not be as detailed as bottom-up for accuracy.

  • Three-point estimating

    Why it's wrong here

    Three-point estimating improves accuracy with ranges but still relies on estimates of individual activities.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE are techniques used for estimating activity durations?

hard
  • A.Three-point estimating
  • B.Parametric estimating
  • C.Reserve analysis
  • D.Monte Carlo simulation
  • E.Analogous estimating

Why A: The correct techniques for estimating activity durations are three-point estimating (A), parametric estimating (B), and analogous estimating (E). Three-point estimating uses optimistic, pessimistic, and most likely estimates. Parametric estimating uses a statistical relationship between historical data and other variables. Analogous estimating uses values from previous similar projects. Reserve analysis (C) is used for contingency reserves, not for estimating durations. Monte Carlo simulation (D) is a risk analysis technique.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.