Sample questions
Certified Associate in Project Management CAPM practice questions
Using the risk register entry shown, what is the expected monetary value (EMV) of this risk?
Which TWO of the following are examples of project constraints? (Choose two.)
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →A project manager is estimating activity durations for a software development project. The team has historical data from similar projects, but the current project involves new tech…
In a project to implement a new customer relationship management (CRM) system, the business analyst needs to understand the current workflows and identify areas for improvement. Wh…
A project is in the monitoring and controlling phase. The project manager calculates the cost performance index (CPI) as 0.8 and the schedule performance index (SPI) as 1.0. The pr…
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →A business analyst is using a requirements management tool to store and track requirements. During a review, the BA notices that two stakeholders have conflicting requirements for…
A project team is struggling with unclear roles and responsibilities, leading to duplicated work and missed tasks. Which document should the project manager create or update to res…
Project Management Fundamentals and Core ConceptseasySee the answer and why each option is right or wrong →A project has a critical path duration of 45 days. Activity X on the critical path can be crashed by 3 days at an additional cost of $500 per day. Activity Y, a non-critical activi…
Which TWO are core practices of Extreme Programming (XP)?
A business analyst is creating a requirements traceability matrix. Which purpose does this serve?
Drag and drop the steps for conducting a procurement process in the correct order.
A project manager is estimating the duration of a task using parametric estimation. Historical data shows that a similar task took 10 hours per unit, and 50 units are required. The…
A manufacturing company is planning to install a new production line using a predictive project management approach. The project has a fixed price contract with a supplier for a cr…
You are a business analyst on a project to develop a new online banking portal. The project is using a hybrid approach with both predictive and adaptive elements. The requirements…
During project execution, a key stakeholder requests a change that would add a new feature to the product. The project manager evaluates the impact on scope, schedule, and cost. Ac…
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →A project manager notices that the project is behind schedule. Which of the following actions is most appropriate to bring the project back on track?
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →Drag and drop the steps for managing project communications in the correct order.
A business analyst is using a business analysis framework to identify stakeholders. Which technique is most effective for ensuring all affected parties are considered?
During stakeholder analysis, a business analyst identifies a key stakeholder who rarely speaks in meetings but provides detailed written feedback. Which engagement strategy is most…
In earned value management, if the Cost Performance Index (CPI) is 0.8 and the Schedule Performance Index (SPI) is 1.2, what does this indicate?
Project Management Fundamentals and Core ConceptshardSee the answer and why each option is right or wrong →A project manager is managing a complex IT project with many inter-dependencies. During execution, a key stakeholder requests a feature that will require rework of several complete…
Project Management Fundamentals and Core ConceptshardSee the answer and why each option is right or wrong →Which THREE of the following are characteristics of a project?
Project Management Fundamentals and Core ConceptsmediumSee the answer and why each option is right or wrong →Refer to the exhibit. How many work packages are at the lowest level of the WBS?
Project Management Fundamentals and Core ConceptseasySee the answer and why each option is right or wrong →Which TWO of the following are considered business analysis planning activities?