Courseiva
Predictive Plan-Based MethodologieshardMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is evaluating the impact of a potential risk on project objectives. The risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$15,000

Expected monetary value is probability times impact, so $15,000. Option A is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $15,000

    Why this is correct

    EMV = 0.3 x $50,000 = $15,000.

  • $50,000

    Why it's wrong here

    This is just the impact, not multiplied by probability.

  • $150,000

    Why it's wrong here

    This would be 3 x $50,000, incorrect.

  • $1,500

    Why it's wrong here

    This is 0.03 x $50,000, incorrect.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.