Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is evaluating the impact of a potential risk on project objectives. The risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

⚠ Common exam trap

CAPM often tests the confusion between impact and EMV, where candidates mistakenly select the impact value ($50,000) instead of multiplying by probability, or misplace the decimal when converting the probability (0.3) to a percentage.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

$15,000

The expected monetary value (EMV) of a risk is calculated by multiplying the probability of the risk occurring by its potential impact. In this case, the probability is 0.3 and the impact is $50,000, so EMV = 0.3 × $50,000 = $15,000. This quantifies the average expected loss or gain from the risk, which is used in decision-making and contingency reserve planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    $15,000

    Why this is correct

    EMV multiplies probability by monetary impact, so 0.3 × $50,000 yields $15,000. This quantifies the risk's expected cost exposure against project objectives, giving the project manager a comparable figure for contingency reserves and risk prioritisation within the risk register.

  • ✗

    $50,000

    Why it's wrong here

    This restates the impact alone, ignoring the 0.3 probability entirely; EMV requires multiplying the two values to give $15,000. It is tempting because impact is the headline risk figure, but EMV weights it by likelihood, so an unweighted impact is not the expected monetary value.

  • ✗

    $150,000

    Why it's wrong here

    Multiplying probability by impact gives $15,000, not $150,000; this option appears to divide impact by probability, an operation EMV never uses. It is tempting because dividing figures feels like a valid risk calculation, yet EMV is strictly probability times monetary impact.

  • ✗

    $1,500

    Why it's wrong here

    Multiplying 0.3 by $50,000 yields $15,000, not $1,500; this option misplaces the decimal point. It is tempting because it still multiplies probability by impact, the correct EMV formula, but the arithmetic is wrong by a factor of ten.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.