Question 306 of 503
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board

In predictive (waterfall) project management, any change that impacts scope, budget, or schedule must follow a formal change control process. The project manager first assesses the impact, then submits a change request to the Change Control Board (CCB) for approval before any action is taken. Implementing the change or updating baselines without CCB approval violates the control scope process defined in the PMBOK Guide.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement the change and update the project plan

    Why it's wrong here

    Changes must be approved before implementation.

  • Submit a change request to the change control board

    Why this is correct

    Formal change request is the first step.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Update the project baseline immediately

    Why it's wrong here

    Baseline update requires approval.

  • Reject the change because it impacts the baseline

    Why it's wrong here

    Rejection without formal process is not proper.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates assume the project manager has the authority to approve or reject changes that impact baselines, but in predictive methodologies, only the CCB can make that decision after a formal change request is submitted.

Detailed technical explanation

How to think about this question

The Perform Integrated Change Control process (PMBOK 4.6) mandates that all change requests be reviewed by the CCB, which has authority to approve, reject, or defer changes. The project manager acts as the evaluator and submitter, not the decision-maker. In real-world scenarios, skipping the CCB can lead to scope creep, budget overruns, and audit failures, especially in regulated industries like healthcare or finance where baselines are contractually binding.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request to the change control board — In predictive (waterfall) project management, any change that impacts scope, budget, or schedule must follow a formal change control process. The project manager first assesses the impact, then submits a change request to the Change Control Board (CCB) for approval before any action is taken. Implementing the change or updating baselines without CCB approval violates the control scope process defined in the PMBOK Guide.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.