A project team using a Kanban board wants to predict when all remaining backlog items will be completed. Which metric is most useful for this prediction?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Cycle time

Cycle time measures the time from when work starts on an item until it is completed, providing a reliable basis for forecasting completion of items in a flow-based system like Kanban. Option C is correct. Velocity (A) is used in Scrum and is not directly applicable to Kanban's flow-based approach. Cumulative flow diagram (B) visualizes WIP and cycle time but does not directly predict completion as effectively as cycle time itself. Lead time (D) includes waiting time before work starts, making it less precise for predicting completion once work is in progress.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Velocity

    Why it's wrong here

    Velocity measures story points completed per iteration in Scrum; Kanban does not use iterations or estimate in points, so it cannot forecast backlog completion here. Velocity is correct for sprint-based Scrum teams predicting capacity, not for continuous-flow Kanban forecasting.

  • ✗

    Cumulative flow diagram

    Why it's wrong here

    A cumulative flow diagram visualises work-in-progress and bottlenecks over time, but does not itself produce a completion forecast. It supports flow analysis. Forecasting remaining backlog completion requires throughput data; the CFD is diagnostic, used to spot accumulating queues rather than to calculate a finish date.

  • ✓

    Cycle time

    Why this is correct

    Cycle time measures the elapsed duration to complete one backlog item, so averaging it across remaining items yields a throughput-based completion forecast. This satisfies the need to predict when all remaining backlog items finish, unlike cumulative flow or velocity metrics.

  • ✗

    Lead time

    Why it's wrong here

    Lead time measures elapsed time from work starting to finishing for individual items, not the rate at which items are completed. Forecasting remaining backlog needs throughput. Lead time is correct for assessing delivery responsiveness or service-level expectations per item, not total completion.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.