Based on the exhibit, what is the critical path duration of the project?
Exhibit
Refer to the exhibit. ``` Activity | Predecessor | Duration (days) A | None | 5 B | A | 3 C | A | 4 D | B, C | 2 E | D | 1 ```
Trap 1: 10 days
This path (A→C→F→H) has a duration of 10 days, but it is not the critical path because there are longer paths.
Trap 2: 11 days
This is the duration of path A-B-D-E, which is not the longest.
Trap 3: 13 days
No path has 13 days duration.
- A
10 days
Why wrong: This path (A→C→F→H) has a duration of 10 days, but it is not the critical path because there are longer paths.
- B
11 days
Why wrong: This is the duration of path A-B-D-E, which is not the longest.
- C
12 days
Path A-C-D-E is 12 days, the longest path.
- D
13 days
Why wrong: No path has 13 days duration.