CAPM · topic practice

Predictive Plan-Based Methodologies practice questions

Practise Certified Associate in Project Management CAPM Predictive Plan-Based Methodologies practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Reviewed byJohnson Ajibi· MSc IT Security
20 questionsDomain: Predictive Plan-Based Methodologies

What the exam tests

What to know about Predictive Plan-Based Methodologies

Predictive Plan-Based Methodologies questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Predictive Plan-Based Methodologies exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Practice set

Predictive Plan-Based Methodologies questions

20 questions · select your answer, then reveal the explanation

Question 1easymultiple choice
Read the full NAT/PAT explanation →

A project manager is developing the project schedule for a construction project. The team has identified all activities and their dependencies. Which tool should the project manager use to determine the critical path?

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What should the project manager do first?

A project manager is estimating activity durations for a software development project. The team has historical data from similar projects, but the current project involves new technology that could cause delays. Which estimating technique should the project manager use to account for uncertainty?

A project manager is creating the risk management plan. Which document should the project manager reference to identify the risk tolerance of stakeholders?

During project planning, the team identifies that a task has a duration of 10 days, a predecessor finish-to-start relationship, and a lag of 2 days. What is the earliest the successor task can start if the predecessor starts on day 1?

Which TWO of the following are outputs of the Define Activities process? (Select exactly 2.)

Which THREE of the following are tools and techniques used in the Control Schedule process? (Select exactly 3.)

A project manager is developing the project schedule for a construction project. The team has identified that the foundation work must be completed before the framing can begin. Which type of dependency does this represent?

During the execution phase of a software development project, the team discovers a critical bug that requires an immediate fix. The project manager uses the contingency reserve to address this. Which plan-based process is being applied?

A project manager is reviewing the project's cost performance. The actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $60,000. What is the cost variance (CV)?

A project manager is creating the project schedule. The team estimates that the optimistic time for an activity is 10 days, the pessimistic time is 30 days, and the most likely time is 15 days. Using PERT three-point estimation, what is the expected duration?

Which TWO of the following are characteristics of a predictive life cycle?

Which THREE of the following are tools and techniques used in the Control Schedule process?

A project manager is planning a project and needs to identify all the work required to complete the project successfully. Which document is the primary output of the Create WBS process?

A project manager is developing a work breakdown structure (WBS) for a software development project. The team is struggling with defining the lowest-level work packages. Which technique should the project manager use to ensure the WBS is complete and properly decomposed?

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What is the first step the project manager should take?

A project manager is using a predictive approach for a construction project. The team has completed 40% of the work, but the actual cost is $500,000 against a planned value of $450,000. The project manager calculates the cost performance index (CPI) and schedule performance index (SPI). Which conclusion is correct?

Which TWO of the following are outputs of the Define Activities process?

Question 19hardmultiple choice
Read the full NAT/PAT explanation →

Based on the exhibit, what is the critical path duration of the project?

Exhibit

Refer to the exhibit.

```
Activity | Predecessor | Duration (days)
A        | None        | 5
B        | A           | 3
C        | A           | 4
D        | B, C        | 2
E        | D           | 1
```

You are managing a predictive project to build a new office building. The project is in the execution phase. During a weekly progress meeting, the electrical contractor reports that a critical piece of switchgear has a 6-week lead time, but it was not ordered because the team assumed it would be procured later. The project schedule shows the switchgear installation activity is supposed to start in 4 weeks. The project manager reviews the procurement management plan and realizes the procurement process was not followed. The project has a tight deadline and cannot accommodate a 6-week delay. What is the best course of action for the project manager?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Predictive Plan-Based Methodologies sessions

Start a Predictive Plan-Based Methodologies only practice session

Every question in these sessions is drawn from the Predictive Plan-Based Methodologies domain — nothing else.

Related practice questions

Related CAPM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the CAPM exam test about Predictive Plan-Based Methodologies?
Predictive Plan-Based Methodologies questions test whether you can apply the concept in context, not just recognise a definition.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Predictive Plan-Based Methodologies questions in a focused session?
Yes — the session launcher on this page draws every question from the Predictive Plan-Based Methodologies domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other CAPM topics?
Use the topic links above to move to related areas, or go back to the CAPM question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the CAPM exam covers. They are not copied from any real exam or dump site.