Courseiva

CAPM · topic practice

Predictive Plan-Based Methodologies practice questions

This CAPM domain covers predictive, plan-based project management: developing the project management plan, collecting requirements, defining scope, sequencing activities, estimating durations and costs, and controlling changes. Questions present scenarios—supplier delays, risk responses, PERT estimates, EMV—and ask you to apply PMBOK-aligned tools and techniques to select the correct action or value.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Predictive Plan-Based Methodologies

What the exam tests

What to know about Predictive Plan-Based Methodologies

You must be able to apply predictive planning tools: build a WBS, sequence activities, estimate durations with PERT, quantify risk with EMV, and choose the right risk response. The single most important thing is matching the correct PMBOK technique to the scenario rather than relying on intuition.

Selecting appropriate risk response strategies—avoid, transfer, mitigate, accept—for high-probability, high-impact risks

Applying PERT three-point estimating: (optimistic + 4×most likely + pessimistic) ÷ 6

Calculating expected monetary value as probability multiplied by impact

Using the project management plan, WBS, and schedule baseline to manage scope, time, and cost changes

Watch out for

Common Predictive Plan-Based Methodologies exam traps

  • ▸Confusing risk mitigation with avoidance: mitigation reduces probability or impact, while avoidance eliminates the threat entirely by changing the plan.
  • ▸Miscomputing PERT by using a simple average of the three estimates instead of the weighted formula with four times the most likely.
  • ▸Treating EMV as a guaranteed loss rather than a probability-weighted expected value used to compare risk exposure across options.

Practice set

Predictive Plan-Based Methodologies questions

20 questions · select your answer, then reveal the explanation

A project manager is creating the risk management plan. Which document should the project manager reference to identify the risk tolerance of stakeholders?

During project planning, the team identifies that a task has a duration of 10 days, a predecessor finish-to-start relationship, and a lag of 2 days. What is the earliest the successor task can start if the predecessor starts on day 1?

During the execution phase of a software development project, the team discovers a critical bug that requires an immediate fix. The project manager uses the contingency reserve to address this. Which plan-based process is being applied?

Which TWO of the following are characteristics of a predictive life cycle?

A project manager is using a predictive approach for a construction project. The team has completed 40% of the work, but the actual cost is $500,000 against a planned value of $450,000. The project manager calculates the cost performance index (CPI) and schedule performance index (SPI). Which conclusion is correct?

Based on the exhibit, what is the critical path duration of the project?

Exhibit

Refer to the exhibit.

```
Activity | Predecessor | Duration (days)
A        | None        | 5
B        | A           | 3
C        | A           | 4
D        | B, C        | 2
E        | D           | 1
```

Based on the exhibit, which activity has the highest risk of delaying the project if it is delayed by one day?

Exhibit

Refer to the exhibit.

Project Schedule (in days):
Activity | Duration | Predecessors | ES | EF | LS | LF | Float
A        | 5        | None         | 0  | 5  | 0  | 5  | 0
B        | 3        | A            | 5  | 8  | 5  | 8  | 0
C        | 2        | A            | 5  | 7  | 6  | 8  | 1
D        | 4        | B, C         | 8  | 12 | 8  | 12 | 0
E        | 3        | D            | 12 | 15 | 12 | 15 | 0

Match each project management methodology to its characteristic.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Sequential phases with little iteration

Iterative and incremental delivery

Time-boxed sprints with daily standups

Visual workflow with WIP limits

Process-based with defined roles

Match each project constraint to its typical trade-off.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

What work is included

Time available for completion

Budget allocated

Standards to be met

People and equipment available

A project manager in a predictive manufacturing project needs to procure a specialized component. The procurement process requires a detailed statement of work (SOW) and firm fixed price (FFP) contract. What should the project manager create first?

Which THREE of the following are key components of a work breakdown structure (WBS) dictionary?

Based on the exhibit, what is the critical path duration?

Exhibit

Refer to the exhibit.

Exhibit:
```
Task ID | Predecessor | Duration (days)
A      | None        | 3
B      | A           | 4
C      | A           | 2
D      | B, C        | 5
E      | D           | 2
F      | D           | 3
G      | E, F        | 1
```

Based on the exhibit, which risk should the project manager prioritize for proactive response?

Exhibit

Refer to the exhibit.

Exhibit:
```
Risk Register Snippet:
Risk ID | Description | Probability | Impact | Score | Response
R001   | Server outage | High (0.7) | High (0.8) | 0.56 | Mitigate: redundant servers
R002   | Staff turnover | Medium (0.5) | Medium (0.5) | 0.25 | Transfer: outsourcing
R003   | Regulatory change | Low (0.2) | High (0.8) | 0.16 | Accept: monitor
```

Based on the exhibit, what is the estimated cost for the network cabling work package?

Exhibit

Refer to the exhibit.

Exhibit:
```
WBS Dictionary Entry:
WBS ID: 1.2.3
Work Package: Install network cabling
Description: Run Cat6 cables from server room to all workstations.
Responsible: IT Infrastructure Team
Duration: 10 days
Cost: $15,000
Acceptance Criteria: All cables tested and certified.
```

A project has a critical path duration of 45 days. Activity X on the critical path can be crashed by 3 days at an additional cost of $500 per day. Activity Y, a non-critical activity with 10 days of float, can also be crashed by 3 days at $600 per day. The project manager wants to reduce the project duration by 3 days at minimum cost. What should the project manager do?

Which TWO of the following are tools and techniques used in the Plan Schedule Management process?

How many work packages are at WBS level 2 (the second level) in this exhibit?

Exhibit

Refer to the exhibit.
```json
{
  "WBS": {
    "1.0 Project": {
      "1.1 Planning": {
        "1.1.1 Requirements",
        "1.1.2 Design"
      },
      "1.2 Execution": {
        "1.2.1 Development",
        "1.2.2 Testing"
      },
      "1.3 Closure": {
        "1.3.1 Deployment",
        "1.3.2 Handover"
      }
    }
  }
}
```

Based on the schedule network shown in the exhibit, what is the critical path?

Exhibit

Refer to the exhibit.
```
Activity | Duration (days) | Predecessor
A        | 5               | -
B        | 3               | A
C        | 4               | A
D        | 2               | B, C
E        | 1               | D
```

Using the risk register entry shown, what is the expected monetary value (EMV) of this risk?

Exhibit

Refer to the exhibit.
```json
{
  "risk_id": "R001",
  "description": "Server hardware failure",
  "probability": "0.8",
  "impact": "High",
  "cost_impact_usd": 50000,
  "response": "Mitigate: Redundant servers"
}
```

During the execution phase of a predictive project, the team discovers that a key deliverable does not meet the acceptance criteria defined in the project management plan. What is the FIRST step the project manager should take?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Predictive Plan-Based Methodologies sessions

Start a Predictive Plan-Based Methodologies only practice session

Every question in these sessions is drawn from the Predictive Plan-Based Methodologies domain — nothing else.

Related practice questions

Related CAPM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the CAPM exam test about Predictive Plan-Based Methodologies?
You must be able to apply predictive planning tools: build a WBS, sequence activities, estimate durations with PERT, quantify risk with EMV, and choose the right risk response. The single most important thing is matching the correct PMBOK technique to the scenario rather than relying on intuition.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Predictive Plan-Based Methodologies questions in a focused session?
Yes — the session launcher on this page draws every question from the Predictive Plan-Based Methodologies domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other CAPM topics?
Use the topic links above to move to related areas, or go back to the CAPM question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the CAPM exam covers. They are not copied from any real exam or dump site.