Courseiva
Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

Which document formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter is the document that formally authorizes the project and gives the project manager the authority to apply organizational resources. Option B (project management plan) guides execution but does not authorize. Option C (business case) provides justification. Option D (scope statement) details scope but does not authorize.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why this is correct

    The project charter formally authorizes the project and the project manager.

  • Project management plan

    Why it's wrong here

    The PM plan describes how the project will be executed but is created after authorization.

  • Business case

    Why it's wrong here

    The business case provides economic justification but does not formally authorize the project.

  • Project scope statement

    Why it's wrong here

    The scope statement defines the scope but does not authorize the project.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which document formally authorizes the project manager to use organizational resources to execute the project?

easy
  • A.Project charter
  • B.Business case
  • C.Scope statement
  • D.Project management plan

Why A: The project charter is the document that formally authorizes the project and the project manager to apply resources to project activities. The project management plan guides execution but does not authorize. The scope statement and business case are inputs.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.