A project manager is developing a project schedule for a software development project using a predictive approach. After identifying activities and sequencing them, what is the NEXT step?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Estimate activity durations

After sequencing activities, the next process is to estimate activity durations, then develop schedule. Option D is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Control schedule

    Why it's wrong here

    Control schedule is during monitoring and controlling.

  • Define activities

    Why it's wrong here

    Define activities occurs before sequencing.

  • Develop schedule

    Why it's wrong here

    Develop schedule comes after estimating durations.

  • Estimate activity durations

    Why this is correct

    This is the next step after sequencing activities.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.