CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which TWO of the following are typically outputs of the Initiating process group?
⚠ Common exam trap
Candidates often confuse the outputs of Initiating with those of Planning, mistakenly selecting the project management plan or WBS because they are foundational documents, but they are formally created later in the Planning process group.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter is a key output of the Initiating process group because it formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. The stakeholder register is also an output of Initiating, as it identifies all stakeholders and their relevant information, which is essential for planning stakeholder engagement.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Work breakdown structure
Why it's wrong here
The Work Breakdown Structure (WBS) is created during the Planning process group, not Initiating, because it decomposes scope defined after the project charter is approved. It tempts because it is a foundational document produced early in the project lifecycle, but the Initiating group outputs only the project charter and stakeholder register, not detailed scope decomposition.
- ✗
Project management plan
Why it's wrong here
The project management plan is developed during Planning.
- ✓
Project charter
Why this is correct
The project charter is developed in the Initiating group.
- ✗
Risk register
Why it's wrong here
Risk register is first created during Planning.
- ✓
Stakeholder register
Why this is correct
Identify Stakeholders is an Initiating process that produces the stakeholder register.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.