Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is estimating activity durations for a new software development project. The manager has data from three similar previous projects, but the new project is slightly larger in scope. Which estimating technique is most appropriate given the available data?

⚠ Common exam trap

CAPM often tests the confusion between analogous and parametric estimating; candidates may pick parametric because it sounds more precise, but the key differentiator is the availability of historical data from similar projects, not a statistical relationship.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimating

Analogous estimating uses historical data from similar past projects to estimate durations for the current project. Since the project manager has data from three similar projects and the new project is only slightly larger, analogous estimating is the most appropriate technique. It is quick, cost-effective, and relies on expert judgment and historical analogies.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Analogous estimating

    Why this is correct

    Analogous estimating uses duration data from comparable past projects to forecast the new one, which suits the limited historical data and slight scope difference. It is less accurate than parametric or three-point estimating but requires minimal detail.

  • ✗

    Parametric estimating

    Why it's wrong here

    Parametric estimating applies a unit rate multiplied by a quantity, requiring a measurable cost or duration driver such as lines of code or function points. The stem supplies three comparable completed projects, not a statistical rate, so analogous estimating using their actual durations scaled for scope is the fit.

  • ✗

    Three-point estimating

    Why it's wrong here

    Three-point estimating produces optimistic, pessimistic and most likely durations for a single activity, so it captures uncertainty rather than leveraging the three comparable historical projects. It would be the right choice when no analogous data exists and the team must quantify risk ranges from expert judgement alone.

  • ✗

    Bottom-up estimating

    Why it's wrong here

    Bottom-up estimating decomposes the project into work packages and sums individual estimates, which discards the three completed similar projects entirely. It suits novel or poorly understood work where no historical baseline exists, not a slightly larger variant of three well-documented predecessors.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.