Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is leading a construction project with a fixed budget and strict deadline. During execution, a key supplier notifies that a critical material will be delayed by two weeks, which will push the project past the deadline. The project manager reviews the schedule and identifies that the delay can be compensated by fast-tracking two subsequent activities that are currently planned sequentially. What should the project manager do first?

⚠ Common exam trap

The trap here is that candidates may immediately choose to add resources (Option D) or accept the delay (Option A) without recognizing that the PMBOK Guide prescribes risk assessment as the mandatory first step before implementing any schedule compression technique.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Assess the risks of fast-tracking the two activities.

The correct first step is to assess the risks of fast-tracking the two activities (Option B). Fast-tracking involves performing activities in parallel that were originally planned sequentially, which can introduce new risks such as rework, resource conflicts, or quality issues. The PMBOK Guide emphasizes that before implementing a schedule compression technique, the project manager must evaluate the associated risks and determine if the benefits outweigh the potential negative impacts. Since the project has a fixed budget and strict deadline, a risk assessment ensures informed decision-making before proceeding.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Accept the delay and update the project schedule accordingly.

    Why it's wrong here

    Accepting delay should be a last resort after evaluating compression options.

  • Assess the risks of fast-tracking the two activities.

    Why this is correct

    Fast-tracking increases risk, so risk assessment must precede implementation.

  • Submit a change request to extend the deadline.

    Why it's wrong here

    A change request should be considered only after determining that schedule compression is not possible or acceptable.

  • Immediately add resources to the delayed activity to catch up.

    Why it's wrong here

    Crashing (adding resources) is a different technique and may not be feasible due to budget constraints.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.