During a predictive project, a team member reports that a critical path activity is behind schedule by two days. To recover the schedule, the project manager should first:

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform schedule compression analysis

The first step is to analyze potential options for schedule compression before taking action.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Perform schedule compression analysis

    Why this is correct

    Correct: Analyzing compression options (fast-tracking, crashing) is the initial step.

  • Fast-track the project

    Why it's wrong here

    Fast-tracking may introduce risk; analysis is needed first.

  • Add resources to the critical path

    Why it's wrong here

    Crashing can be effective but should not be the first step without analysis.

  • Accept the delay and update the baseline

    Why it's wrong here

    Acceptance should be a last resort after considering compression.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.