Courseiva

CAPM Cost Variance (CV) Practice Question

A project has a cost baseline of $100,000. At the end of month 2, the planned value is $30,000, and the actual cost is $40,000. If the earned value is $25,000, what is the cost variance?

⚠ Common exam trap

Candidates often confuse cost variance with schedule variance or miscalculate by using Planned Value instead of Actual Cost. Always use EV - AC for CV.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

-$15,000

Cost variance (CV) = Earned Value (EV) - Actual Cost (AC) = $25,000 - $40,000 = -$15,000. A negative CV indicates the project is over budget. Therefore, option C is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $15,000

    Why it's wrong here

    Positive CV would mean under budget, but here it's over budget.

  • -$10,000

    Why it's wrong here

    Incorrect calculation.

  • -$15,000

    Why this is correct

    Correct calculation of CV.

  • $10,000

    Why it's wrong here

    This is the EV minus PV? Incorrect.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.