Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which THREE of the following are components of the project charter?

⚠ Common exam trap

PMI often tests the distinction between high-level charter content and detailed planning outputs, so candidates mistakenly select detailed schedule or WBS because they confuse the Initiating and Planning process groups.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project purpose or justification

The project charter formally authorizes the project and the project manager. It includes the project purpose or justification (A) to establish the business need, a summary budget (B) to provide high-level financial constraints, and high-level risks (D) to identify potential uncertainties early. These are key components per the PMBOK Guide.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project purpose or justification

    Why this is correct

    The project purpose or justification states why the project is undertaken and the business need it addresses, authorising the project manager to proceed. It satisfies the scenario as a recognised charter component, alongside the summary budget and high-level risks.

  • ✓

    Summary budget

    Why this is correct

    The summary budget gives the approved high-level financial envelope for the project, against which the project manager later develops the detailed cost baseline. It satisfies the scenario as a recognised charter component, alongside the project purpose and high-level risks.

  • ✗

    Detailed project schedule

    Why it's wrong here

    The charter authorises the project and names its high-level scope, objectives, stakeholders and constraints; the schedule is produced later during planning, after scope decomposition. A schedule would be the right artefact once activities, durations and dependencies are defined, but it cannot precede the charter that approves the work.

  • ✓

    High-level risks

    Why this is correct

    High-level risks identify the major uncertainties known at initiation, giving the project manager visibility before detailed risk planning begins. It satisfies the scenario as a recognised charter component, alongside the project purpose and summary budget.

  • ✗

    Work breakdown structure

    Why it's wrong here

    The charter stays high-level, capturing purpose, measurable objectives, boundaries and authority; the WBS decomposes scope into deliverables and is created during planning. A WBS is the correct artefact for detailed scope breakdown, but including it in the charter would pre-empt planning and exceed the charter's authorising role.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.