CAPM Predictive Plan-Based Methodologies Practice Question
In a predictive project management approach, which TWO artifacts are components of the project management plan?
⚠ Common exam trap
Test-takers frequently confuse project documents (like the lessons learned register or requirements traceability matrix) with components of the project management plan, but the PMBOK Guide clearly distinguishes between the two categories, and the exam expects you to know which artifacts are formally part of the plan versus supporting documents.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule baseline
The schedule baseline (option A) is a component of the project management plan as it represents the approved schedule model used to measure performance. The work breakdown structure dictionary (option D) is also a component, as it provides detailed information about each WBS element and is part of the scope baseline, which is a key component of the project management plan. In predictive (waterfall) project management, both baselines are formally integrated into the plan and are subject to change control processes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule baseline
Why this is correct
The schedule baseline is a key component of the project management plan.
- ✗
Lessons learned register
Why it's wrong here
The lessons learned register is a project document, not part of the project management plan.
- ✗
Requirements traceability matrix
Why it's wrong here
The requirements traceability matrix is a project document, not a component of the project management plan.
- ✓
Work breakdown structure dictionary
Why this is correct
This is part of the scope baseline, which is a component of the project management plan.
- ✗
Project charter
Why it's wrong here
The project charter is an input to develop the project management plan, but it is not a component of the plan itself.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.