Courseiva
Agile Frameworks and MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Agile Frameworks and Methodologies Practice Question

During a sprint review, the team demonstrates a new feature to stakeholders. One stakeholder says, 'This isn't what we wanted. We need a completely different approach.' The product owner is upset because the feature took two weeks to build. The team is frustrated because they followed the product owner's specifications exactly. The Scrum Master observes that the product owner did not involve stakeholders during the sprint and based the user stories on assumptions. The product owner wants to add the rework to the next sprint. However, the team's capacity is already full. The Scrum Master needs to help the team and product owner recover. What should the Scrum Master do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Coach the product owner to collaborate with stakeholders during the sprint to validate assumptions early

The root cause is lack of stakeholder involvement during the sprint. The Scrum Master should encourage the product owner to engage stakeholders regularly, perhaps by showing early increments or holding more frequent demos. Adding rework without adjusting scope will cause the team to fail the next sprint. Blaming the team is inappropriate. Instead, the product owner should renegotiate the sprint goal with the team.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Remove the product owner from the project to prevent future miscommunication

    Why it's wrong here

    Removing the product owner violates the Scrum framework’s principle that the product owner is a single accountable role for maximising value; the correct first step is to facilitate a conversation to align stakeholder expectations with backlog priorities, not to eliminate the role. This option is tempting because it offers a swift, punitive fix for repeated miscommunication, and it would be correct only if the product owner had demonstrated persistent, irremediable negligence that the Scrum Master had already attempted to resolve through coaching and process improvement.

  • Blame the team for not clarifying requirements during the sprint

    Why it's wrong here

    The team acted on the product owner's specifications; blame is not constructive.

  • Coach the product owner to collaborate with stakeholders during the sprint to validate assumptions early

    Why this is correct

    Early and frequent feedback prevents such surprises; the product owner should show progress more often.

  • Add the rework to the next sprint and ask the team to work overtime

    Why it's wrong here

    Adding work without removing other items will lead to overcommitment and quality issues.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.