Courseiva

CAPM Business Analysis Frameworks Practice Question

A business analyst is creating a business case for a new project. Which of the following is a key component that must be included in the business case?

⚠ Common exam trap

CAPM often tests the distinction between pre-project documents (business case, benefits management plan) and planning documents (risk register, milestones, user stories), and candidates confuse artifacts from later phases with business case components.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Cost-benefit analysis and financial metrics

A business case is the document that justifies the investment in a project, and its core component is the cost-benefit analysis with financial metrics such as ROI, NPV, IRR, and payback period. These quantify whether the project is worth funding and are the primary decision-making input for stakeholders.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    User stories and acceptance criteria

    Why it's wrong here

    User stories and acceptance criteria belong to requirements elicitation and backlog definition, produced after the business case is approved. A business case instead needs the problem statement, options analysis, costs, benefits and risks that justify funding. Confusing the two is tempting because both documents describe the project's intended value.

  • ✗

    Project milestones and deliverables

    Why it's wrong here

    Milestones and deliverables belong to the project schedule and scope baseline, not the business case, which justifies why the investment should proceed. It is tempting because deliverables describe the intended outcome, yet the business case must instead capture benefits, costs, risks and strategic alignment.

  • ✓

    Cost-benefit analysis and financial metrics

    Why this is correct

    A business case justifies investment by weighing expected benefits against costs, so cost-benefit analysis with financial metrics such as ROI, payback period and NPV provides the quantitative evidence decision-makers need to approve, reject or prioritise the project.

  • ✗

    Risk register and risk responses

    Why it's wrong here

    The risk register is a project management artefact produced during planning and maintained throughout execution, not a required component of the business case, which justifies the investment. It is tempting because risk identification does inform the business case, but the register itself belongs to the project management plan.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.