Drag and drop the steps for creating a work breakdown structure (WBS) in the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Identify deliverables, then Decompose deliverables into work packages, then Structure in a hierarchical form, then Assign WBS codes, then Verify completeness
The WBS is built by identifying deliverables, decomposing them, structuring hierarchically, coding elements, and verifying completeness.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Identify deliverables, then Decompose deliverables into work packages, then Structure in a hierarchical form, then Assign WBS codes, then Verify completeness
Why this is correct
This is the correct order because the WBS process starts with identifying all deliverables, then breaking them down into smaller work packages, organizing them hierarchically, assigning codes for tracking, and finally verifying completeness to ensure all project work is covered.
- ✗
Structure in a hierarchical form, then Identify deliverables, then Decompose deliverables into work packages, then Assign WBS codes, then Verify completeness
Why it's wrong here
This is incorrect because structuring the hierarchy before identifying deliverables and decomposing them puts the cart before the horse; you need to know what the deliverables are before organizing them.
- ✗
Identify deliverables, then Assign WBS codes, then Decompose deliverables into work packages, then Structure in a hierarchical form, then Verify completeness
Why it's wrong here
This is incorrect because assigning WBS codes should occur after decomposition and structuring, not before; codes are used to label the work packages and levels in the hierarchy.
- ✗
Decompose deliverables into work packages, then Identify deliverables, then Structure in a hierarchical form, then Assign WBS codes, then Verify completeness
Why it's wrong here
This is incorrect because decomposition of deliverables cannot happen before the deliverables are identified; you must first know what the deliverables are before breaking them down.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.