Courseiva
Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What is the first step the project manager should take?

⚠ Common exam trap

PMI often tests the misconception that a key stakeholder's request should be automatically approved or that the project manager can make unilateral decisions on scope changes, when in fact the formal change control process must always be followed regardless of stakeholder importance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board

In predictive (waterfall) project management, any change that impacts scope, budget, or schedule must follow the formal integrated change control process. The project manager's first step after evaluating the impact is to submit a change request to the change control board (CCB) for approval or rejection. This ensures that all changes are documented, assessed for risks, and aligned with the project baseline before implementation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reject the change due to budget and time constraints

    Why it's wrong here

    The project manager should not unilaterally reject; the change should be formally evaluated.

  • Submit a change request to the change control board

    Why this is correct

    Formal change requests are submitted to the CCB for evaluation and decision.

  • Implement the change and document it later

    Why it's wrong here

    Implementing changes without approval is a violation of change control procedures.

  • Approve the change because the stakeholder is key

    Why it's wrong here

    Approval authority rests with the CCB, not the project manager alone.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.