Question 359 of 503
Agile Frameworks and MethodologieseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is 8 points, which represents the team's remaining capacity for the sprint. This is correct because the velocity remaining capacity calculation subtracts the work already committed from the team’s known velocity; here, 30 points of velocity minus 22 points of committed stories leaves 8 points of available capacity. On the Certified Associate in Project Management CAPM exam, this tests your understanding of how velocity is used as a planning metric in agile frameworks, specifically to avoid overcommitting the team. A common trap is confusing committed work with capacity or mistakenly adding the two values, so remember that remaining capacity is always velocity minus what has already been taken. For a quick memory tip, think of velocity as your team’s full gas tank and committed work as the fuel already used—remaining capacity is simply what’s left in the tank for the sprint.

CAPM Agile Frameworks and Methodologies Practice Question

This CAPM practice question tests your understanding of agile frameworks and methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Exhibit:
Sprint Backlog:
- User Story A: 5 points
- User Story B: 2 points
- User Story C: 10 points
- User Story D: 5 points
Total: 22 points
Team velocity: 30 points per sprint.

Refer to the exhibit. The team's velocity is 30 points per sprint, and they have already committed to stories totaling 22 points. What is the team's remaining capacity for this sprint?

Question 1easymultiple choice
Full question →

Exhibit

Exhibit:
Sprint Backlog:
- User Story A: 5 points
- User Story B: 2 points
- User Story C: 10 points
- User Story D: 5 points
Total: 22 points
Team velocity: 30 points per sprint.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

8 points

Option A is correct because remaining capacity is velocity minus committed work: 30 - 22 = 8 points. Option B is wrong because 30 is the full velocity. Option C is wrong because 22 is committed work, not capacity. Option D is wrong because it adds velocity to committed.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 22 points

    Why it's wrong here

    22 points is the work already committed.

  • 30 points

    Why it's wrong here

    30 points is the full velocity, not remaining.

  • 8 points

    Why this is correct

    30 - 22 = 8 points remaining capacity.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 52 points

    Why it's wrong here

    52 is the sum of velocity and committed work.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Agile Frameworks and Methodologies — This question tests Agile Frameworks and Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 8 points — Option A is correct because remaining capacity is velocity minus committed work: 30 - 22 = 8 points. Option B is wrong because 30 is the full velocity. Option C is wrong because 22 is committed work, not capacity. Option D is wrong because it adds velocity to committed.

What should I do if I get this CAPM question wrong?

Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.