Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project manager is leading a project to implement a new customer relationship management (CRM) system. The project is in the execution phase. The project manager notices that a team member is consistently late in completing assigned tasks, causing delays. What is the most appropriate action for the project manager to take first?

⚠ Common exam trap

The trap here is jumping to escalation or reassignment without first diagnosing the problem through direct communication.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Discuss the issue with the team member to understand the cause

When a team member's performance affects project progress, the project manager should first engage in direct communication to uncover the underlying cause. This approach aligns with the principles of team management and conflict resolution, emphasizing collaboration and problem-solving. Only after understanding the issue can the project manager determine the appropriate corrective action, such as providing support, clarifying expectations, or involving functional management if necessary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Discuss the issue with the team member to understand the cause

    Why this is correct

    The project manager should first communicate directly with the team member to identify the reasons for the delays. This could be due to lack of resources, unclear expectations, personal issues, or skill gaps. Addressing the root cause is essential for a sustainable solution and aligns with effective team management and conflict resolution.

  • ✗

    Reassign the team member's tasks to other team members

    Why it's wrong here

    Reassigning tasks may resolve the immediate delay but does not address the root cause of the team member's lateness. It could also demotivate the team member and set a precedent for avoiding responsibility. The project manager should first understand why the team member is late before taking corrective action.

  • ✗

    Escalate the issue to the functional manager immediately

    Why it's wrong here

    Escalating immediately may be premature and could damage the working relationship with the team member. The project manager should first attempt to resolve the issue directly. Escalation is typically a last resort after other methods have failed or if the issue is beyond the project manager's authority.

  • ✗

    Update the issue log and continue monitoring the situation

    Why it's wrong here

    Logging the issue is important, but simply monitoring without taking action does not resolve the problem. The project manager needs to proactively address the performance issue. Logging is a part of the process, but direct communication should occur first to understand and correct the behavior.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.