Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

During project execution, a key stakeholder requests a significant change that will increase project scope. The project manager performs an impact analysis and determines that the change will delay the project by two weeks and increase costs by 10%. However, the change is critical for regulatory compliance. What should the project manager do first?

⚠ Common exam trap

Test-takers frequently assume a critical compliance need automatically justifies bypassing the change control process, but the CAPM exam strictly tests adherence to formal procedures regardless of urgency.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the change request to the change control board (CCB).

The correct first step is to submit the change request to the change control board (CCB) because, in formal project management, any change that impacts scope, schedule, or cost must go through the integrated change control process. Even though the change is critical for regulatory compliance, the project manager cannot unilaterally approve or reject it; the CCB has the authority to evaluate the impact analysis and make the final decision.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approve the change because it is critical for compliance.

    Why it's wrong here

    Changes affecting baselines require CCB approval.

  • Reject the change because it will delay the project and increase costs.

    Why it's wrong here

    Regulatory compliance may override schedule/cost concerns; must be evaluated by CCB.

  • Submit the change request to the change control board (CCB).

    Why this is correct

    Formal change control process requires CCB review and decision.

  • Implement the change and request approval after.

    Why it's wrong here

    Unauthorized changes violate change control procedures.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.