Question 432 of 503

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a key stakeholder requests a significant change that will increase project scope. The project manager performs an impact analysis and determines that the change will delay the project by two weeks and increase costs by 10%. However, the change is critical for regulatory compliance. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit the change request to the change control board (CCB).

The correct first step is to submit the change request to the change control board (CCB) because, in formal project management, any change that impacts scope, schedule, or cost must go through the integrated change control process. Even though the change is critical for regulatory compliance, the project manager cannot unilaterally approve or reject it; the CCB has the authority to evaluate the impact analysis and make the final decision.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approve the change because it is critical for compliance.

    Why it's wrong here

    Changes affecting baselines require CCB approval.

  • Reject the change because it will delay the project and increase costs.

    Why it's wrong here

    Regulatory compliance may override schedule/cost concerns; must be evaluated by CCB.

  • Submit the change request to the change control board (CCB).

    Why this is correct

    Formal change control process requires CCB review and decision.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Implement the change and request approval after.

    Why it's wrong here

    Unauthorized changes violate change control procedures.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates assume a critical compliance need automatically justifies bypassing the change control process, but the CAPM exam strictly tests adherence to formal procedures regardless of urgency.

Detailed technical explanation

How to think about this question

The integrated change control process is defined in the PMBOK Guide as a key component of project integration management. It ensures that all changes are documented, reviewed, and approved or rejected by the CCB, which typically includes stakeholders with the authority to balance competing constraints like scope, time, cost, and quality. In real-world scenarios, regulatory changes often require expedited review, but the formal process still applies to maintain audit trails and accountability.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit the change request to the change control board (CCB). — The correct first step is to submit the change request to the change control board (CCB) because, in formal project management, any change that impacts scope, schedule, or cost must go through the integrated change control process. Even though the change is critical for regulatory compliance, the project manager cannot unilaterally approve or reject it; the CCB has the authority to evaluate the impact analysis and make the final decision.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.