A project manager is using a predictive approach to manage a project. During the execution phase, the team is working on deliverables. Which process group involves tracking, reviewing, and regulating progress against the plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Monitoring and Controlling Process Group

The Monitoring and Controlling Process Group involves tracking, reviewing, and regulating progress against the plan. Option A is correct because this process group ensures that project objectives are met by measuring performance and applying corrective actions. The Planning Process Group (B) establishes the scope and plan; the Executing Process Group (C) involves completing the work; and the Initiating Process Group (D) defines the project. Therefore, only Monitoring and Controlling fits the described activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Monitoring and Controlling Process Group

    Why this is correct

    Monitoring and Controlling tracks, reviews and regulates project performance against the plan, comparing actual progress with baselines and initiating change requests. It spans execution, giving the predictive project its mechanism for measuring deliverable progress and correcting deviations.

  • ✗

    Planning Process Group

    Why it's wrong here

    Planning establishes the scope, schedule and baseline; it does not track or regulate progress once work is underway. It is tempting because planning defines what will be measured, but the monitoring and controlling process group performs the tracking, review and regulation the question describes.

  • ✗

    Executing Process Group

    Why it's wrong here

    Executing is where the work is performed to produce deliverables, not where progress is tracked and regulated against the plan. It is tempting because the scenario mentions the execution phase, but monitoring and controlling is the process group that compares actual performance with the baseline and initiates corrective action.

  • ✗

    Initiating Process Group

    Why it's wrong here

    Initiating authorises the project or phase and defines its high-level scope; it performs no tracking or regulation of execution progress. It is tempting because it starts the predictive lifecycle, but monitoring and controlling is the process group that measures performance against the plan and manages changes.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.