Courseiva
Predictive Plan-Based MethodologiesmediumMultiple SelectObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is using a predictive approach to manage project costs. Which THREE of the following are cost estimation techniques? (Select THREE)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analogous estimating

Analogous, bottom-up, and parametric are cost estimation techniques. Options A, C, E are correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Analogous estimating

    Why this is correct

    Correct: Analogous is a cost estimation technique.

  • Earned value management

    Why it's wrong here

    Incorrect: EVM is a performance measurement, not estimation.

  • Bottom-up estimating

    Why this is correct

    Correct: Bottom-up is a cost estimation technique.

  • Cost-benefit analysis

    Why it's wrong here

    Incorrect: Cost-benefit analysis is used for project selection.

  • Parametric estimating

    Why this is correct

    Correct: Parametric is a cost estimation technique.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.